| 8.1 INSTALLED CAPACITY OF ELECTRICITY IN GUJARAT STATE | 8.1 INSTALLED CAPACITY OF ELECTRICITY IN GUJARAT STATE | ||||||||||||||||||||||
| (In MW) | (In MW) | ||||||||||||||||||||||
| Sr. | As on | Gujarat Electricity Board | Central | Total | Sr. | ||||||||||||||||||
| No. | 31st March | Hydro | Steam | Gas | Diesel | Total | GSECL | AEC | GIPCL | ESSAR | GTEC | GSEG | Bhav. | Total | Sector | Installed | No. | ||||||
| of the Year | and | Ele | Share | Capacity | |||||||||||||||||||
| Wind | Co. | (7+15+16) | |||||||||||||||||||||
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 1 | ||||||
| 1 | 1961 | - | 110.50 | - | 32.50 | 143.00 | - | 157.50 | - | - | - | - | 12.00 | 169.50 | - | 312.50 | 1 | ||||||
| 2 | 1966 | - | 374.50 | - | 10.50 | 385.00 | - | 217.50 | - | - | - | - | 16.00 | 233.50 | - | 618.50 | 2 | ||||||
| 3 | 1969 | - | 384.50 | - | 32.70 | 417.20 | - | 217.50 | - | - | - | - | 16.00 | 233.50 | - | 650.70 | 3 | ||||||
| 4 | 1974 | - | 649.50 | 54.00 | 9.10 | 712.60 | - | 217.50 | - | - | - | - | 16.00 | 233.50 | - | 946.10 | 4 | ||||||
| 5 | 1978 | 300.00 | 1120.50 | 54.00 | - | 1474.50 | - | 217.50 | - | - | - | - | 16.00 | 233.50 | - | 1708.00 | 5 | ||||||
| 6 | 1985 | 300.00 | 2352.50 | 54.00 | - | 2706.50 | - | 400.00 | - | - | - | - | - | 400.00 | 277.00 | 3383.50 | 6 | ||||||
| 7 | 1990 | 365.00 | 3329.00 | 54.00 | - | 3748.00 | - | 495.50 | - | - | - | - | - | 495.50 | 580.00 | 4823.50 | 7 | ||||||
| 8 | 1991 | 425.00 | 3399.00 | 54.00 | - | 3878.00 | - | 482.00 | 32.00 | - | - | - | - | 514.00 | 702.00 | 5094.00 | 8 | ||||||
| 9 | 1992 | 425.00 | 3609.00 | 54.00 | - | 4088.00 | - | 550.00 | 145.00 | - | - | - | - | 695.00 | 810.00 | 5593.00 | 9 | ||||||
| 10 | 1993 | 425.00 | 3729.00 | 114.00 | - | 4268.00 | - | 550.00 | 145.00 | - | - | - | - | 695.00 | 994.50 | 5957.50 | 10 | ||||||
| 11 | 1994 | 427.00 | 3729.00 | 189.00 | - | 4345.00 | - | 550.00 | 145.00 | - | - | - | - | 695.00 | 1100.50 | 6140.50 | 11 | ||||||
| 12 | 1995 | 427.00 | 3729.00 | 189.00 | - | 4345.00 | - | 550.00 | 145.00 | - | - | - | - | 695.00 | 1201.00 | 6241.00 | 12 | ||||||
| 13 | 1996 | 427.00 | 3729.00 | 189.00 | - | 4345.00 | - | 550.00 | 145.00 | - | - | - | - | 695.00 | 1323.00 | 6363.00 | 13 | ||||||
| 14 | 1997 | 427.00 | 3804.00 | 189.00 | - | 4420.00 | - | 550.00 | 145.00 | 192.00 | - | - | - | 887.00 | 1323.00 | 6630.00 | 14 | ||||||
| 15 | 1998 | 487.00 | 3759.00 | 234.00 | - | 4480.00 | 210.00 | 550.00 | 305.00 | 300.00 | 414.00 | - | - | 1779.00 | 1323.00 | 7582.00 | 15 | ||||||
| 16 | 1999 | 547.00 | 3759.00 | 234.00 | - | 4540.00 | 420.00 | 550.00 | 305.00 | 300.00 | 655.00 | - | - | 2230.00 | 1323.00 | 8093.00 | 16 | ||||||
| 17 | 2000 | 547.00 | 3759.00 | 234.00 | - | 4540.00 | 420.00 | 550.00 | 555.00 | 300.00 | 655.00 | - | - | 2480.00 | 1323.00 | 8343.00 | 17 | ||||||
| 18 | 2001 | 547.00 | 3759.00 | 234.00 | - | 4540.00 | 420.00 | 550.00 | 555.00 | 300.00 | 655.00 | - | - | 2480.00 | 1562.00 | 8582.00 | 18 | ||||||
| 19 | 2002 | 547.00 | 3759.00 | 207.00 | - | 4513.00 | 420.00 | 490.00 | 555.00 | 300.00 | 655.00 | 156.00 | - | 2576.00 | 1562.00 | 8651.00 | 19 | ||||||
| 20 | 2003 | 547.00 | 3759.00 | 27.00 | - | 4333.00 | 555.00 | 490.00 | 555.00 | 300.00 | 655.00 | 156.00 | - | 2711.00 | 1562.00 | 8606.00 | 20 | ||||||
| 21 | 2003-04* | 547.00 | 3759.00 | 27.00 | - | 4333.00 | 555.00 | 490.00 | 555.00 | 300.00 | 655.00 | 156.00 | - | 2711.00 | 1562.00 | 8606.00 | 21 | ||||||
| * April-October, 2003 | Note : (1) Utran Gas Based Power Station of 135 MW has been taken over by M/s GSECL w.e.f. 01-08-02. | ||||||||||||||||||||||
| Source:- Gujarat Electricity Board, Vadodara. | |||||||||||||||||||||||