| 8.1 INSTALLED CAPACITY OF ELECTRICITY IN
GUJARAT STATE |
|
8.1 INSTALLED CAPACITY OF ELECTRICITY IN
GUJARAT STATE |
|
|
|
|
|
|
|
|
| |
|
|
|
|
(In MW) |
|
|
|
|
|
(In MW) |
|
|
| Sr. |
As on |
|
Gujarat
Electricity Board |
|
|
Central |
Total |
Sr. |
|
| No. |
31st March |
|
Hydro |
Steam |
Gas |
Diesel |
Total |
GSECL |
AEC |
GIPCL |
ESSAR |
GTEC |
GSEG |
Bhav. |
Total |
Sector |
Installed |
No. |
|
|
of the Year |
|
|
and |
|
Ele |
|
Share |
Capacity |
|
|
|
|
|
Wind |
|
Co. |
|
(7+15+16) |
|
|
| 1 |
2 |
|
3 |
4 |
5 |
6 |
7 |
8 |
9 |
10 |
11 |
12 |
13 |
14 |
15 |
16 |
17 |
1 |
|
| 1 |
1961 |
|
- |
110.50 |
- |
32.50 |
143.00 |
- |
157.50 |
- |
- |
- |
- |
12.00 |
169.50 |
- |
312.50 |
1 |
|
| 2 |
1966 |
|
- |
374.50 |
- |
10.50 |
385.00 |
- |
217.50 |
- |
- |
- |
- |
16.00 |
233.50 |
- |
618.50 |
2 |
|
| 3 |
1969 |
|
- |
384.50 |
- |
32.70 |
417.20 |
- |
217.50 |
- |
- |
- |
- |
16.00 |
233.50 |
- |
650.70 |
3 |
|
| 4 |
1974 |
|
- |
649.50 |
54.00 |
9.10 |
712.60 |
- |
217.50 |
- |
- |
- |
- |
16.00 |
233.50 |
- |
946.10 |
4 |
|
| 5 |
1978 |
|
300.00 |
1120.50 |
54.00 |
- |
1474.50 |
- |
217.50 |
- |
- |
- |
- |
16.00 |
233.50 |
- |
1708.00 |
5 |
|
| 6 |
1985 |
|
300.00 |
2352.50 |
54.00 |
- |
2706.50 |
- |
400.00 |
- |
- |
- |
- |
- |
400.00 |
277.00 |
3383.50 |
6 |
|
| 7 |
1990 |
|
365.00 |
3329.00 |
54.00 |
- |
3748.00 |
- |
495.50 |
- |
- |
- |
- |
- |
495.50 |
580.00 |
4823.50 |
7 |
|
| 8 |
1991 |
|
425.00 |
3399.00 |
54.00 |
- |
3878.00 |
- |
482.00 |
32.00 |
- |
- |
- |
- |
514.00 |
702.00 |
5094.00 |
8 |
|
| 9 |
1992 |
|
425.00 |
3609.00 |
54.00 |
- |
4088.00 |
- |
550.00 |
145.00 |
- |
- |
- |
- |
695.00 |
810.00 |
5593.00 |
9 |
|
| 10 |
1993 |
|
425.00 |
3729.00 |
114.00 |
- |
4268.00 |
- |
550.00 |
145.00 |
- |
- |
- |
- |
695.00 |
994.50 |
5957.50 |
10 |
|
| 11 |
1994 |
|
427.00 |
3729.00 |
189.00 |
- |
4345.00 |
- |
550.00 |
145.00 |
- |
- |
- |
- |
695.00 |
1100.50 |
6140.50 |
11 |
|
| 12 |
1995 |
|
427.00 |
3729.00 |
189.00 |
- |
4345.00 |
- |
550.00 |
145.00 |
- |
- |
- |
- |
695.00 |
1201.00 |
6241.00 |
12 |
|
| 13 |
1996 |
|
427.00 |
3729.00 |
189.00 |
- |
4345.00 |
- |
550.00 |
145.00 |
- |
- |
- |
- |
695.00 |
1323.00 |
6363.00 |
13 |
|
| 14 |
1997 |
|
427.00 |
3804.00 |
189.00 |
- |
4420.00 |
- |
550.00 |
145.00 |
192.00 |
- |
- |
- |
887.00 |
1323.00 |
6630.00 |
14 |
|
| 15 |
1998 |
|
487.00 |
3759.00 |
234.00 |
- |
4480.00 |
210.00 |
550.00 |
305.00 |
300.00 |
414.00 |
- |
- |
1779.00 |
1323.00 |
7582.00 |
15 |
|
| 16 |
1999 |
|
547.00 |
3759.00 |
234.00 |
- |
4540.00 |
420.00 |
550.00 |
305.00 |
300.00 |
655.00 |
- |
- |
2230.00 |
1323.00 |
8093.00 |
16 |
|
| 17 |
2000 |
|
547.00 |
3759.00 |
234.00 |
- |
4540.00 |
420.00 |
550.00 |
555.00 |
300.00 |
655.00 |
- |
- |
2480.00 |
1323.00 |
8343.00 |
17 |
|
| 18 |
2001 |
|
547.00 |
3759.00 |
234.00 |
- |
4540.00 |
420.00 |
550.00 |
555.00 |
300.00 |
655.00 |
- |
- |
2480.00 |
1562.00 |
8582.00 |
18 |
|
| 19 |
2002 |
|
547.00 |
3759.00 |
207.00 |
- |
4513.00 |
420.00 |
490.00 |
555.00 |
300.00 |
655.00 |
156.00 |
- |
2576.00 |
1562.00 |
8651.00 |
19 |
|
| 20 |
2003* |
|
547.00 |
3759.00 |
27.00 |
- |
4333.00 |
555.00 |
490.00 |
555.00 |
300.00 |
655.00 |
156.00 |
- |
2711.00 |
1562.00 |
8606.00 |
20 |
|
| * April-November, 2002 |
|
|
|
Source:- Gujarat
Electricity Board, Vadodara. |
|
|
|
|
| Note
: (1) Utran TPS Stage-1 three units of 15 MW capacity each have been retired
w.e.f. 19-9-02 |
|
| (2) Utran Gas Based Power Station
of 135 MW has been taken over by M/s. GSECL, w.e.f. 1-8-02 |
|
|
|
|
|
|
|
|
|
| S-72 |
S-73 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|